Industry News: 1-30-26

It is no secret that BEAD, other federal broadband deployment programs, and now data centers are impacting the fiber supply chain, but an article in Fierce this week highlighted just how significant that impact is. The article cites information from fiber cable manufacturer Superior Essex who said that lead times for ribbon fiber are in the 60-plus weeks range while loose tube fiber is well into the third quarter 2026 range.